Item - 2015.TE7.64
Tracking Status
- City Council adopted this item on July 7, 2015 without amendments.
- This item was considered by the Toronto and East York Community Council on June 16, 2015 and adopted without amendment. It will be considered by City Council on July 7, 2015.
TE7.64 - Revitalizing Yonge - Downtown Yonge Street
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- 27 - Toronto Centre-Rosedale, 28 - Toronto Centre-Rosedale
City Council Decision
City Council on July 7, 8 and 9, 2015, adopted the following:
1. City Council authorize the initiation of a Functional Street Design Study for Yonge Street from Queen Street to Gerrard Street by Transportation Services in consultation with City Planning and with input from other appropriate City Divisions (as described in Downtown Yonge Street Studies - Information Report, dated December 10, 2012) and community stakeholders.
2. City Council receive for information, the report (December 10, 2012) from the Director, Community Planning, Toronto and East York District, entitled "Downtown Yonge Street Studies - Information Report".
3. City Council receive for information, the report (June 11, 2013) from the Acting Director, Transportation Services, Toronto and East York District, entitled "Celebrate Yonge - Post Event Review".
Background Information (Community Council)
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-80860.pdf
Attachment 1-5 - Revitalizing Yonge - Downtown Yonge Street.pdf
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-81073.pdf
(December 10, 2012) Attachment 6 - Report from the Director, Community Planning, Toronto and East York District - Downtown Yonge Street Studies - Information Report
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-80931.pdf
(June 11, 2013) Attachment 7 - Report from the Acting Director, Transportation Services, Toronto and East York District - Celebrate Yonge - Post Event Review
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-80932.pdf
Communications (Community Council)
Communications (City Council)
https://www.toronto.ca/legdocs/mmis/2015/cc/comm/communicationfile-53939.pdf
Motions (City Council)
TE7.64 - Revitalizing Yonge - Downtown Yonge Street
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- 27 - Toronto Centre-Rosedale, 28 - Toronto Centre-Rosedale
Community Council Recommendations
The Toronto and East York Community Council recommends that:
1. City Council authorize the initiation of a Functional Street Design Study for Yonge Street from Queen Street to Gerrard Street by Transportation Services in consultation with City Planning and with input from other appropriate City Divisions (as described in Downtown Yonge Street Studies - Information Report, dated December 10, 2012) and community stakeholders.
2. City Council receive for information, the report (December 10, 2012) from the Director, Community Planning, Toronto and East York District, entitled “Downtown Yonge Street Studies - Information Report”.
3. City Council receive for information, the report (June 11, 2013) from the Acting Director, Transportation Services, Toronto and East York District, entitled “Celebrate Yonge - Post Event Review”.
Origin
Summary
This report recommends that Council authorize staff to initiate a study of Yonge Street from Queen Street to Gerrard Street, to explore design options for streetscaping and public realm improvements that would increase pedestrian space and have regard for cyclists through the narrowing of the roadway, including the potential reduction of traffic lanes. This study would be undertaken as a Functional Street Design Study.
This initiative would inform considerations for potential improvements to the broader Yonge Street corridor outside this segment that serves the Downtown, from Davenport Road to the Waterfront. This broader Yonge Street corridor is being considered as part of the TOcore project, the City's planning and infrastructure study currently underway for the Downtown. The TOcore team will be undertaking a Parks and Public Realm Strategic Master Plan, and will include considerations for public realm improvements along the length of Yonge Street within the Downtown.
This report recommends the Functional Street Design Study be managed by Transportation Services, in consultation with City Planning, and with input from other appropriate City Divisions. This study will commence in 2016 and will be funded from Transportation Services' 2016 capital budget.
Background Information
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-80860.pdf
Attachment 1-5 - Revitalizing Yonge - Downtown Yonge Street.pdf
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-81073.pdf
(December 10, 2012) Attachment 6 - Report from the Director, Community Planning, Toronto and East York District - Downtown Yonge Street Studies - Information Report
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-80931.pdf
(June 11, 2013) Attachment 7 - Report from the Acting Director, Transportation Services, Toronto and East York District - Celebrate Yonge - Post Event Review
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-80932.pdf
Communications
Speakers
Jared Kolb, Executive Director, Cycle Toronto