EX26.32 - Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2017 Capital Budget and 2018-2026 Capital Plan

Decision Type:
ACTION
Status:
Adopted on Consent
Wards:
All

City Council Decision

City Council on July 4, 5, 6  and 7, 2017, adopted the following:

 

1. City Council authorize the reallocation of funds and revise project costs within the Parks, Forestry and Recreation's Approved 2017 Capital Budget and future year commitments in the amount of $3.000 million, as included in Appendix 1 to the report (June 2, 2017) from the General Manager, Parks, Forestry and Recreation, with zero Budget and debt impact.

 

2. City Council authorize the deferral and acceleration of projects in Parks, Forestry and Recreation's Approved 2017 Capital Budget and future year commitments in the amount of $2.186 million, as included in Appendix 2 to the report (June 2, 2017) from the General Manager, Parks, Forestry and Recreation, with zero gross and net debt impact.

 

3. City Council authorize the deferral of the Riverdale Park Access Improvements project, from 2017 to 2018, with funding from the South District Parkland Development Reserve Fund (XR2209) in the amount of $0.750 million and authorize the acceleration of the Sherway Trail project, from 2023 to 2017, with funding from the West District Parkland Development Reserve Fund (XR2203) in the amount of $0.325 million.

 

4. City Council authorize the closure of three completed sub-projects in Parks, Forestry and Recreation's Approved 2017 Capital Budget in the amount of $1.185 million, as included in Appendix 3 to the report (June 2, 2017) from the General Manager, Parks, Forestry and Recreation to reduce 2017 cash flow, and release commitments on development related funding sources to the appropriate accounts.

Background Information (Committee)

(June 2, 2017) Report from the General Manager, Parks, Forestry and Recreation on Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2017 Capital Budget and 2018-2026 Capital Plan
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104787.pdf
Appendix 1 - Adjustments to Cash Flow and Project Cost ($000s)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104788.pdf
Appendix 2 - Deferrals/Accelerations ($000s)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104789.pdf
Appendix 3 - Project Closures ($)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104790.pdf

32a - Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2017 Capital Budget and 2018-2026 Capital Plan

Background Information (Committee)
(June 9, 2017) Letter from the Budget Committee on Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2017 Capital Budget and 2018-2026 Capital Plan
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104917.pdf

EX26.32 - Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2017 Capital Budget and 2018-2026 Capital Plan

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Committee Recommendations

The Executive Committee recommends that:

 

1. City Council authorize the reallocation of funds and revise project costs within the Parks, Forestry and Recreation's 2017 Council Approved Capital Budget and future year commitments in the amount of $3.000 million, as included in Appendix 1 to the report (June 2, 2017) from the General Manager, Parks, Forestry and Recreation, with zero Budget and debt impact.

 

2. City Council authorize the deferral and acceleration of projects in Parks, Forestry and Recreation's 2017 Council Approved Capital Budget and future year commitments in the amount of $2.186 million, as included in Appendix 2 to the report (June 2, 2017) from the General Manager, Parks, Forestry and Recreation, with zero gross and net debt impact.

 

3. City Council authorize the deferral of the Riverdale Park Access Improvements project, from 2017 to 2018, with funding from the South District Parkland Development Reserve Fund (XR2209) in the amount of $0.750 million and authorize the acceleration of the Sherway Trail project, from 2023 to 2017, with funding from the West District Parkland Development Reserve Fund (XR2203) in the amount of $0.325 million.

 

4. City Council authorize the closure of three completed sub-projects in Parks, Forestry and Recreation's 2017 Council Approved Capital Budget in the amount of $1.185 million, as included in Appendix 3 to the report (June 2, 2017) from the General Manager, Parks, Forestry and Recreation to reduce 2017 cash flow, and release commitments on development related funding sources to the appropriate accounts.

Origin

(June 2, 2017) Report from the General Manager, Parks, Forestry and Recreation

Summary

The purpose of this report is to request authority from City Council to amend the approved 2017 Council Approved Capital Budget and 2018-2026 Capital Plan for Parks, Forestry and Recreation (PF&R) by adjusting project costs and cash flows contained within the Budget and Plan.  The adjustments will align cash flows for capital project delivery schedules and program requirements and will have a zero debt impact.  Additional reallocations to project cash flows and project costs are requested where recent project bids exceed the current approved cash flow or alternatively to advance projects into 2017 that are ready to proceed.

 

These reallocations will allow Parks, Forestry and Recreation to continue to deliver projects within its capital plan.  These adjustments will have a zero dollar impact on debt funding and will align the budget and plan with the Parks, Forestry and Recreation capital delivery schedule, the readiness to proceed and the program requirements.

 

In addition, this report seeks Council approval for the closure of three projects that will reduce 2017 cash flow and release the remaining funds for other capital purposes.

Background Information

(June 2, 2017) Report from the General Manager, Parks, Forestry and Recreation on Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2017 Capital Budget and 2018-2026 Capital Plan
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104787.pdf
Appendix 1 - Adjustments to Cash Flow and Project Cost ($000s)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104788.pdf
Appendix 2 - Deferrals/Accelerations ($000s)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104789.pdf
Appendix 3 - Project Closures ($)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104790.pdf

Motions

1 - Motion to Adopt Item moved by Councillor Gary Crawford (Carried)

That the recommendations in the letter (June 9, 2017) from the Budget Committee [Item EX26.32a] be adopted.

32a - Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2017 Capital Budget and 2018-2026 Capital Plan

Origin
(June 9, 2017) Letter from the Budget Committee
Summary

The purpose of this report is to request authority from City Council to amend the approved 2017 Council Approved Capital Budget and 2018-2026 Capital Plan for Parks, Forestry and Recreation (PF&R) by adjusting project costs and cash flows contained within the Budget and Plan.  The adjustments will align cash flows for capital project delivery schedules and program requirements and will have a zero debt impact.  Additional reallocations to project cash flows and project costs are requested where recent project bids exceed the current approved cash flow or alternatively to advance projects into 2017 that are ready to proceed.

 

These reallocations will allow Parks, Forestry and Recreation to continue to deliver projects within its capital plan.  These adjustments will have a zero dollar impact on debt funding and will align the budget and plan with the Parks, Forestry and Recreation capital delivery schedule, the readiness to proceed and the program requirements.

 

In addition, this report seeks Council approval for the closure of three projects that will reduce 2017 cash flow and release the remaining funds for other capital purposes.

Background Information
(June 9, 2017) Letter from the Budget Committee on Adjustments and Deferrals/Accelerations to the Parks, Forestry and Recreation 2017 Capital Budget and 2018-2026 Capital Plan
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-104917.pdf
Source: Toronto City Clerk at www.toronto.ca/council