Item - 2020.TE12.32

Tracking Status

  • City Council adopted this item on January 29, 2020 with amendments.
  • This item was considered by Toronto and East York Community Council on January 8, 2020. It is being forwarded to City Council without recommendations. It will be considered by City Council on January 29, 2020.

TE12.32 - Construction Staging Area Time Extension - 281-289 Avenue Road

Decision Type:
ACTION
Status:
Amended
Ward:
12 - Toronto - St. Paul's

City Council Decision

City Council on January 29, 2020, adopted the following:

 

1. City Council authorize the continuation of the closure of the east sidewalk and a 4.0 metre wide portion of the northbound curb lane on Avenue Road, between a point 40.2 metres south a Cottingham Street and a point 45.6 metres further south and provision of a temporary pedestrian walkway within the closed portion of the northbound curb lane, from February 7, 2020 to August 31, 2020.

 

2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

4. City Council direct that Avenue Road be returned to its pre-construction traffic and parking regulations when the project is complete.

Background Information (Community Council)

(December 12, 2019) Report and Attachment from the Acting Director, Traffic Management, Transportation Services - Construction Staging Area Time Extension - 281-289 Avenue Rd
https://www.toronto.ca/legdocs/mmis/2020/te/bgrd/backgroundfile-141144.pdf

Motions (City Council)

1 - Motion to Adopt Item as Amended moved by Councillor Gord Perks (Carried)

That City Council adopt the following recommendations in the report (December 5, 2019) from the Acting Director, Traffic Management, Transportation Services:

 

1. City Council authorize the continuation of the closure of the east sidewalk and a 4.0 metre wide portion of the northbound curb lane on Avenue Road, between a point 40.2 metres south a Cottingham Street and a point 45.6 metres further south and provision of a temporary pedestrian walkway within the closed portion of the northbound curb lane, from February 7, 2020 to August 31, 2020.

 

2. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

3. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

4. City Council direct that Avenue Road be returned to its pre-construction traffic and parking regulations when the project is complete.

Vote (Adopt Item as Amended) Jan-29-2020 4:32 PM

Result: Carried Majority Required - TE12.32 - Perks - motion 1 - Adopt the item as amended
Total members that voted Yes: 21 Members that voted Yes are Paul Ainslie, Ana Bailão, Brad Bradford, Shelley Carroll, Mike Colle, Gary Crawford, Paula Fletcher, Michael Ford, Mark Grimes, Stephen Holyday, Jim Karygiannis, Cynthia Lai, Mike Layton, Jennifer McKelvie, Denzil Minnan-Wong, Frances Nunziata (Chair), James Pasternak, Gord Perks, Anthony Perruzza, Michael Thompson, John Tory
Total members that voted No: 3 Members that voted No are John Filion, Josh Matlow, Kristyn Wong-Tam
Total members that were Absent: 2 Members that were absent are Joe Cressy, Jaye Robinson

TE12.32 - Construction Staging Area Time Extension - 281-289 Avenue Road

Decision Type:
ACTION
Status:
Without Recs
Ward:
12 - Toronto - St. Paul's

Community Council Recommendations

The Toronto and East York Community Council submits the item to City Council without recommendations.

Origin

(December 5, 2019) Report from the Acting Director, Traffic Management, Transportation Services

Summary

As the Toronto Transit Commission (TTC) operates a transit service on Avenue Road, City Council approval of this report is required.

 

Davies Development Corp. is constructing a nine-storey residential development at 281-289 Avenue Road. The sidewalk and a portion of the northbound curb lane on the east side of Avenue Road fronting the site are currently closed to accommodate construction staging operations for the development. City Council, at its meeting on January 30 and 31, 2019, authorized the subject construction staging area from February 6, 2019 to February 6, 2020.

 

Transportation Services is requesting authorization to extend the construction staging area on Avenue Road for an additional seven months (i.e. from February 7, 2020 to August 31, 2020), in order to complete the construction of the development.

 

The developer has requested an extension of the duration of the construction staging area on Avenue Road, as the site has experienced a number of construction delays encountered during the excavation and shoring phase.

Background Information

(December 12, 2019) Report and Attachment from the Acting Director, Traffic Management, Transportation Services - Construction Staging Area Time Extension - 281-289 Avenue Rd
https://www.toronto.ca/legdocs/mmis/2020/te/bgrd/backgroundfile-141144.pdf

Motions

Motion to forward item Without Recommendations moved by Councillor Josh Matlow (Carried)

That the item be forwarded to City Council without recommendation.

Source: Toronto City Clerk at www.toronto.ca/council