Item - 2021.TE26.43

Tracking Status

  • This item was considered by Toronto and East York Community Council on June 24, 2021. The Toronto and East York Community Council postponed consideration of this item. Consult the text of the decision for further information on the deferral.

TE26.43 - Construction Staging Area Time Extension - 39-41 Roehampton Avenue

Decision Type:
ACTION
Status:
Deferred
Schedule Type:
Delegated
Ward:
12 - Toronto - St. Paul's

Community Council Decision

The Toronto and East York Community Council deferred consideration of the item until its September 9, 2021 meeting.

Origin

(May 18, 2021) Report from the Acting Director, Traffic Management, Transportation Services

Summary

This staff report is about a matter that Community Council has delegated authority to make a final decision.

 

TMG Builders is constructing a 46-storey residential condominium building at 39-41 Roehampton Avenue. The south sidewalk and a 1.5-metre-wide portion of the eastbound curb lane on Roehampton Avenue, between a point 86.5 metres east of Yonge Street and a point 34.5 metres further east is currently closed for construction staging operations. A temporary pedestrian walkway is provided within the closed portion of the eastbound curb lane. Toronto and East York Community Council, at its meeting on October 11, 2019, approved the subject staging area from October 11, 2019 to July 31, 2021.

 

The developer has requested an extension of the duration of the construction staging area on Roehampton Avenue, in order to complete the construction of the development. Based on the information provided by the developer, the site has experienced a number of construction delays due to COVID-19.

 

Transportation Services is requesting authorization to extend the duration of the construction staging area on Roehampton Avenue for an additional seven months (August 1, 2021 to February 28, 2022) in order to complete the construction of the development.

Background Information

(May 18, 2021) Report and Attachment 1 from the Acting Director, Traffic Management, Transportation Services - Construction Staging Area Time Extension - 39-41 Roehampton Avenue
https://www.toronto.ca/legdocs/mmis/2021/te/bgrd/backgroundfile-167709.pdf

Motions

1 - Motion to Defer Item moved by Councillor Josh Matlow (Carried)

That the Toronto and East York Community Council:

 

1. Defer consideration of this item to the September 9, 2021 meeting of Toronto and East York Community Council.