AU5.6 - The Deep Lake Water Cooling Project - Total City Costs and Benefits Need to Be Reported

Decision Type:
ACTION
Status:
Adopted on Consent
Wards:
All

City Council Decision

City Council on February 6 and 7, 2012, adopted the following:

 

1.         City Council request the General Manager, Toronto Water to report to City Council all operating and capital costs incurred by Toronto Water on the Deep Lake Water Cooling Project along with the estimated benefits.

 

2.         City Council request the Executive Director, Facilities Management, to conduct an evaluation of City facilities to determine whether or not financial and environmental benefits from deep lake cooling have been achieved.

Background Information (Committee)

(October 10, 2011) Report from the Auditor General on The Deep Lake Water Cooling Project - Total City Costs and Benefits Need to be Reported
https://www.toronto.ca/legdocs/mmis/2011/au/bgrd/backgroundfile-42377.pdf
(October 10, 2011) Appendix 1 - Management's Response to the Auditor General's Review of The Deep Lake Water Cooling Project - Total City Costs and Benefits Need to be Reported
https://www.toronto.ca/legdocs/mmis/2011/au/bgrd/backgroundfile-42378.pdf

AU5.6 - The Deep Lake Water Cooling Project - Total City Costs and Benefits Need to Be Reported

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Committee Recommendations

The Audit Committee recommends that:

 

1.         City Council request the General Manager, Toronto Water to report to City Council all operating and capital costs incurred by Toronto Water on the Deep Lake Water Cooling Project along with the estimated benefits.

 

2.         City Council request the Executive Director, Facilities Management, to conduct an evaluation of City facilities to determine whether or not financial and environmental benefits from deep lake cooling have been achieved.

Origin

(October 10, 2011) Report from the Auditor General

Summary

This report includes the results of the Auditor General’s Review of the agreement between the City of Toronto and Enwave Energy Corporation in regards to the City’s financial involvement in the Deep Lake Water Cooling Project.  The focus of the review has been on whether or not the City costs of the project as well as the environmental benefits of the project have been clearly articulated and reported to City Council.

 

In summary there needs to be a clear and complete disclosure of all City costs to City Council and in particular for those City buildings subject to deep lake water cooling there needs to be an analysis to determine if costs and benefits have met original objectives.

Background Information

(October 10, 2011) Report from the Auditor General on The Deep Lake Water Cooling Project - Total City Costs and Benefits Need to be Reported
https://www.toronto.ca/legdocs/mmis/2011/au/bgrd/backgroundfile-42377.pdf
(October 10, 2011) Appendix 1 - Management's Response to the Auditor General's Review of The Deep Lake Water Cooling Project - Total City Costs and Benefits Need to be Reported
https://www.toronto.ca/legdocs/mmis/2011/au/bgrd/backgroundfile-42378.pdf

Motions

1 - Motion to Adopt Item moved by Councillor Mary-Margaret McMahon (Carried)