TE4.44 - Construction Staging Area - 1220 Dundas Street East

Decision Type:
ACTION
Status:
Adopted
Ward:
30 - Toronto-Danforth

City Council Decision

City Council on March 31, April 1 and 2, 2015, adopted the following:

 

1.         City Council approve the closure of the sidewalk on the north side of Dundas Street East, between a point 70.4 metres east of Carlaw Avenue and a point 125.2 metres east of Carlaw Avenue, from February 11, 2015 to December 31, 2015.

 

2.         City Council direct that Dundas Street East be returned to its pre-construction traffic and parking regulations when the project is complete.

 

3.         City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

4.         City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

Background Information (Community Council)

(December 4, 2014) Report from the Director, Transportation Services, Toronto and East York District - Construction Staging Area - 1220 Dundas Street East
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-74814.pdf
Drawing No. 421G-1602 - Construction Staging Area - 1220 Dundas Street East
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-74815.pdf

Communications (Community Council)

(December 19, 2014) E-mail from Laurence Lui (TE.Main.TE4.44.1)
(January 11, 2015) E-mail from Sylvia Slaughter (TE.Main.TE4.44.2)
(January 12, 2015) E-mail from Michael Holloway (TE.Main.TE4.44.3)

Motions (City Council)

Motion to Adopt Item (Carried)

TE4.44 - Construction Staging Area - 1220 Dundas Street East

Decision Type:
ACTION
Status:
Amended
Ward:
30 - Toronto-Danforth

Community Council Recommendations

The Toronto and East York Community Council recommends that:

 

1.         City Council approve the closure of the sidewalk on the north side of Dundas Street East, between a point 70.4 metres east of Carlaw Avenue and a point 125.2 metres east of Carlaw Avenue, from February 11, 2015 to December 31, 2015.

 

2.         City Council direct that Dundas Street East be returned to its pre-construction traffic and parking regulations when the project is complete.

 

3.         City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

4.         City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

Origin

(December 4, 2014) Report from the Director, Transportation Services, Toronto and East York District

Summary

Streetcar Developments is constructing a 7-storey condominium at No. 1220 Dundas Street East.  They need to close the sidewalk and a bicycle lane on the north side of Dundas Street East and establish a temporary pedestrian walkway in the bicycle lane in order to do their work.

Background Information

(December 4, 2014) Report from the Director, Transportation Services, Toronto and East York District - Construction Staging Area - 1220 Dundas Street East
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-74814.pdf
Drawing No. 421G-1602 - Construction Staging Area - 1220 Dundas Street East
https://www.toronto.ca/legdocs/mmis/2015/te/bgrd/backgroundfile-74815.pdf

Communications

(December 19, 2014) E-mail from Laurence Lui (TE.Main.TE4.44.1)
(January 11, 2015) E-mail from Sylvia Slaughter (TE.Main.TE4.44.2)
(January 12, 2015) E-mail from Michael Holloway (TE.Main.TE4.44.3)

Motions

1 - Motion to Amend Item moved by Councillor Paula Fletcher (Carried)

That the Toronto and East York Community Council recommend that City Council adopt the recommendations in the report (December 4, 2014) from the Director, Transportation Services, Toronto and East York District, subject to:

 

A.        Amending Recommendation 1 to read as follows:

 

"1.        City Council approve the closure of the sidewalk on the north side of Dundas Street East, between a point 70.4 metres east of Carlaw Avenue and a point 125.2 metres east of Carlaw Avenue, from February 11, 2015 to December 31, 2015."

 

B.        Adding the following new Recommendations 3 and 4.

 

"3.        City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

4.         City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor."

Source: Toronto City Clerk at www.toronto.ca/council