Item - 2016.EX15.23
Tracking Status
- City Council adopted this item on June 7, 2016 without amendments.
- This item was considered by the Executive Committee on May 24, 2016 and adopted without amendment. It will be considered by City Council on June 7, 2016.
EX15.23 - Overhaul of 30 Canadian Light Rail Vehicles and Maintaining Non-Overhauled Streetcars in a State of Good Repair
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
City Council Decision
City Council on June 7, 8 and 9, 2016, adopted the following:
1. City Council approve the overhaul of 30 Canadian Light Rail Vehicles as a Capital Project at an estimated final cost of $9.1 million.
2. City Council approve the refurbishment of critical mechanical, pneumatic and electrical components to maintain the non-overhauled Canadian Light Rail Vehicles in a state of good repair at an operating cost of $17.5 million.
3. City Council approve the refurbishment of critical mechanical, pneumatic and electrical components to maintain the non-overhauled Articulated Light Rail Vehicles in a state of good repair at an operating cost of $7.5 million.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2016/ex/bgrd/backgroundfile-92031.pdf
(March 23, 2016) Report from the Chief Executive Officer on Overhaul of 30 Canadian Light Rail Vehicles (CLRV) and Maintaining Non-Overhauled Streetcars in a State of Good Repair
https://www.toronto.ca/legdocs/mmis/2016/ex/bgrd/backgroundfile-92032.pdf
Motions (City Council)
EX15.23 - Overhaul of 30 Canadian Light Rail Vehicles and Maintaining Non-Overhauled Streetcars in a State of Good Repair
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council approve the overhaul of thirty (30) Canadian Light Rail Vehicles (CLRVs) as a Capital Project at an estimated final cost of $9.1 million.
2. City Council approve the refurbishment of critical mechanical, pneumatic and electrical components to maintain the non-overhauled Canadian Light Rail Vehicles (CLRVs) in a state of good repair at an operating cost of $17.5 million.
3. City Council approve the refurbishment of critical mechanical, pneumatic and electrical components to maintain the non-overhauled Articulated Light Rail Vehicles (ALRVs) in a state of good repair at an operating cost of $7.5 million.
Origin
Summary
At its meeting on Wednesday, March 23, 2016 the Toronto Transit Commission Board considered the attached report entitled, "Overhaul of 30 Canadian Light Rail Vehicles (CLRV) and Maintaining non-Overhauled Streetcars in a State of Good Repair". The Board approved the recommendation in the staff report, as follows:
It is recommended that the Toronto Transit Commission Board approve:
1. Overhaul of thirty (30) Canadian Light Rail Vehicles (CLRVs) as a Capital Project at an estimated final cost (EFC) of $9.1 million;
2. Refurbishment of critical mechanical, pneumatic and electrical components to maintain the non-overhauled CLRVs in a state of good repair at an operating cost of $17.5 million;
3. Refurbishment of critical mechanical, pneumatic and electrical components to maintain the non-overhauled Articulated Light Rail Vehicles (ALRVs) in a state of good repair at an operating cost of $7.5 million;
4. Staff to proceed with the identified work in advance of Council approval in order to meet and maintain Streetcar service;
5. Staff to accrue costs and apply these costs to future claims allowed for in the Bombardier Transportation contract under liquidated damages; and
6. Submission of this report to City of Toronto Council for approval.
The foregoing is forwarded for the approval of City of Toronto Council.
Background Information
https://www.toronto.ca/legdocs/mmis/2016/ex/bgrd/backgroundfile-92031.pdf
(March 23, 2016) Report from the Chief Executive Officer on Overhaul of 30 Canadian Light Rail Vehicles (CLRV) and Maintaining Non-Overhauled Streetcars in a State of Good Repair
https://www.toronto.ca/legdocs/mmis/2016/ex/bgrd/backgroundfile-92032.pdf