  • City Council adopted this item on February 2, 2022 without amendments.

MM39.25 - Strathearn Road Reconstruction Contract 20ECS-TI-104LR - Postponing Installation of New Sidewalk - by Councillor Josh Matlow, seconded by Councillor Mike Colle

Decision Type:
ACTION
Status:
Adopted
Ward:
12 - Toronto - St. Paul's

City Council Decision

City Council on February 2 and 3, 2022, adopted the following:

 

1.  City Council direct the General Manager, Transportation Services and the Chief Engineer and Executive Director, Engineering and Construction Services, to postpone the planned installation of a new sidewalk on the south side Strathearn Road, between Bathurst Street and Glen Cedar Road through the removal of this scope from the active road construction contract, and that consideration of this location for a new sidewalk be reconsidered at a future time with reduced impact to the mature trees and landscaping features.

Background Information (City Council)

Motions (City Council)

Motion to Introduce Motion without Notice moved by Councillor Josh Matlow (Carried)

That Councillor Matlow be permitted to add to the agenda of today's meeting an urgent Motion without Notice concerning:

 

Strathearn Road Reconstruction Contract 20ECS-TI-104LR - Postponing Installation of New Sidewalk

 

Reason for Urgency:

 

This Motion is urgent as the reconstruction on Strathearn Road has begun (is imminent).


Motion to Adopt Item (Carried)